BILL NO. 17-0751st R.

Agenda Title:

17-075 - 1R. An ordinance authorizing a contract with Blue Nile Contractors, Inc., in the amount of $478,847.00; for the installation of pipe and water main on 23rd street, from Trail Ridge to West of Hub Dr.; and authorizing future minor change orders not to exceed $47,885.00; and/or time extensions.

Recommendations:

Council approval is recommended to award the contract for the installation of 1,884 ft. of 12" ductile iron pipe, 91 ft. of  8" ductile iron pipe and 342 ft. of 6" ductile iron water main on 23rd Street from Trail Ridge to West of Hub Drive to Blue Nile Contractors, Inc.
Background:

The existing 12 inch cast iron water main was installed in 1953 and is located under the pavement of 23rd Street from Trail Ridge to West of Hub Drive. This section of main has had three leaks in the last eight years resulting in thousands of dollars in repairs. The Water Department is proposing to install a new 12 inch ductile iron water pipe along the south side of 23rd Street out side of the pavement.

 

The  Water Department is recommending this contract be awarded to Blue Nile Contractors, Inc. Blue Nile Contractors, Inc. has done other projects for the Water Department in the past. The Water Department was very pleased with the quality of their work.



Fiscal Impact:

The funds for this project will come from the Water Fund Net Assets - Water Capital Budget Account No. 70401301.





Department:          WATERContact Person:          Dan Montgomery


REVIEWERS:
DepartmentAction
Water DepartmentApproved
Finance DepartmentApproved
Finance DepartmentApproved
Law DepartmentApproved
City Managers OfficeApproved
City Clerk DepartmentApproved

Council Action:          Council Action:         

ATTACHMENTS:
Description
Ordinance
Bidders List